At the beginning of Q4 2021, although the COVID-19 pandemic was gradually being brought under control across Vietnam, the situation remained complex in many localities. Many businesses continued to adopt “Work from Home” and “Three-on-the-Spot” working arrangements at their offices, factories, and construction sites.

Despite these challenges, driven by our strong determination to overcome adversity and, above all, our commitment to construction schedules with our valued Investors, all employees of Koastal Eco continued working tirelessly at 150% capacity to ensure that construction of the three projects awarded in Q3 2021 could commence as scheduled.

The three projects include:

  • Phase 1 Centralized WWTP at Khai Quang Industrial Park, with a capacity of 7,000 m³/day, Vinh Phuc Province;
  • Phase 2 Centralized WWTP at Amata Song Khoai Industrial Park, with a capacity of 4,000 m³/day, Quang Ninh Province;
  • Centralized WWTP for Japfa’s largest livestock slaughtering and meat processing plant in Vietnam, located in Binh Phuoc Province, with a capacity of 4,850 m³/day.

With the strong focus and dedication of the KEI Team, these projects are on track to meet the completion schedules committed to our valued Investors.

By contributing to the development of synchronized infrastructure for industrial parks and manufacturing facilities, these projects will help create favorable conditions for attracting further investment while providing businesses with greater confidence and stability in their production and operations.